(PLANNING PERMISSION PHASE 1: 23/3188; PHASE 2: 23/2811)

Construction continues to progress at High Road Wembley, with the central core of Building 1 advancing and the level 5 and 6 slabs due to be completed by the end of the month.

Work is continuing across the development, with SFS and curtain walling now underway at ground and level 1. Pile caps for Building 2 are also nearing completion, with the lower ground floor slab and columns to level 1 due to be cast in the coming weeks.

Our timelapse camera continues to capture progress at High Road Wembley and will document key stages throughout the development.

We look forward to sharing further updates as the project continues to move forward.